This free ARE 5.0 study guide teaches to the Architect Registration Examination — all six NCARB divisions, organized the way the exam is built.[1] The ARE is one of three pillars of architectural licensure (alongside an accredited degree and the AXP experience program), and it is broad and demanding, so this guide is deep: real teaching of contracts, codes, systems, and construction administration — not a summary.
And it’s interactive, not a wall of text: every division has a built-in checkpoint quiz, hover-able glossary terms, labeled diagrams, and concept questions, so you learn by doing.
Read it division by division, test yourself at each checkpoint, then round out your free ARE 5.0 study resources with our practice questions and flashcards.
ARE 5.0 Exam Snapshot
| Detail | Architect Registration Examination 5.0 |
|---|---|
| Divisions | 6 separate exams: PcM, PjM, PA, PPD, PDD, CE (taken in any order) |
| Items per division | 65 to 100 items (490 total across all six) |
| Question types | Multiple choice, check-all-that-apply, hotspot, plus 2 case studies per division |
| Time per division | About 2 hr 40 min to 4 hr 5 min of testing, plus flexible break time |
| Passing standard | Pass/fail per division against a cut score (no published percentage) |
| 2024 pass rates | About 47% to 61% by division; ~55% overall |
| Delivery | Computer-based, through PSI test centers and online proctoring |
| Certifying body | National Council of Architectural Registration Boards (NCARB) |
| Cost | A fee per division (verify the current amount at NCARB.org/fees) |
| Retakes | Retake a failed division after 60 days; up to 3 attempts per division in any 12 months |
The exam is split into six divisions that follow the life of a project, from running a practice through closing out construction. You take each as a separate appointment, and you can sit them in any order.[1] The two largest divisions, PPD and PDD, carry 100 items each:
Each division is a separate exam you schedule, pay for, and pass on its own. They follow the progression of a real architecture project, from running a practice to closing out construction.
- PcMPractice Management65 items
- PjMProject Management75 items
- PAProgramming & Analysis75 items
- PPDProject Planning & Design100 items
- PDDProject Development & Documentation100 items
- CEConstruction & Evaluation75 items
Pass all six divisions — in any order — to become ARE complete (490 items total).
Within each division, NCARB publishes content sections with their own weight ranges — and those weights tell you where to spend study time. This guide teaches all six divisions and, inside each, leads with the heaviest sections.[1]
The divisions trace the life of a project. Most of what they test maps onto the design and construction phases below — knowing this sequence is the backbone that ties the six exams together:
- 1. Schematic Design (SD)Establish overall scope, scale, and relationships — site organization, massing, preliminary plans.
- 2. Design Development (DD)Refine systems, materials, and sizes so the design is ready to document.
- 3. Construction Documents (CD)Produce the drawings and specifications used to permit, bid, and build.
- 4. Bidding / NegotiationPrice the work through competitive bids or negotiation; award the construction contract.
- 5. Construction Administration (CA)Observe the work, review submittals and RFIs, certify payment, and manage changes.
Each phase locks in more decisions — and makes later owner changes more expensive.
1 · Practice Management (PcM)
65 items · 2 hr 40 min. PcM is about running an architecture practice — its business and legal structure, finances, ethics, risk, and how it delivers services. The heaviest section is Finances, Risk & Development of Practice (29–35%), followed by service delivery and business operations.[5]
Business Operations & Firm Structures
A firm’s legal structure sets its liability and taxes. A sole proprietorship is one owner with unlimited personal liability and pass-through tax. A partnership shares profits and unlimited liability among partners.
A corporation is a separate legal entity that shields owners but is taxed separately, and a blends a corporation’s liability shield with pass-through taxation. Many states require a professional corporation (PC) for licensed practice — but no structure shields an architect from liability for their own professional negligence.
| Structure | Liability | Taxation |
|---|---|---|
| Sole proprietorship | Unlimited personal | Pass-through |
| General partnership | Unlimited, joint | Pass-through |
| LLC | Limited to the entity | Pass-through (flexible) |
| Corporation / PC | Limited (not for own malpractice) | Separate (or S-corp pass-through) |
Firm Finances & Risk
Firm finances are tested through a handful of ratios. is the indirect cost of doing business (rent, non-billable salaries, insurance), and the overhead rate is overhead divided by direct labor. The — net revenue divided by direct labor — shows how much revenue each dollar of billable labor generates, and the (chargeable ratio) is billable labor divided by total labor.
| Measure | How it is found | What it tells you |
|---|---|---|
| Overhead rate | Indirect cost / direct labor | Cost burden per dollar of billable labor |
| Break-even rate | 1.0 + overhead rate | Multiplier that covers cost with no profit |
| Net multiplier | Net revenue / direct labor | Revenue earned per dollar of direct labor (~3.0 is common) |
| Utilization rate | Billable labor / total labor | Share of staff time charged to projects |
Risk management runs through PcM. Architects limit exposure with clear scope,, professional liability (errors and omissions) insurance written on a claims-made basis, limitation-of-liability and indemnification clauses, quality control, and good documentation. The statute of repose sets an absolute outer deadline for claims measured from substantial completion.
Ethics & the Standard of Care
The is the legal benchmark: the skill and diligence a reasonably prudent architect would use under similar circumstances. It does not demand perfection — meeting it generally defeats a negligence claim. The AIA Code of Ethics adds enforceable duties to the public, the client, the profession, colleagues, and the environment, organized into canons, ethical standards, and rules of conduct.
Practice-Wide Delivery of Services
How a firm gets and delivers work matters: marketing builds reputation, business development pursues specific clients, and a go/no-go decision weighs fit, profitability, and risk before chasing a project. Compensation methods — stipulated (fixed) sum, hourly with a not-to-exceed cap, and percentage of construction cost — each shift risk differently, and a clear distinction between basic and additional services protects the fee when scope grows.
Checkpoint · Division 1 · Practice Management
Question 1 of 10
In a professional negligence claim against an architect, what does the legal concept of the standard of care establish?
2 · Project Management (PjM)
75 items · 3 hr. PjM is about managing a single project — its team, work plan, schedule, and especially its contracts, which is the heaviest section (25–31%), followed by quality control and execution.[6]
Project Work Planning & Scheduling
A project work plan defines scope, deliverables, staffing, schedule, and budget — the baseline for tracking progress and profit. Scheduling uses the critical path method: the critical path is the longest chain of dependent tasks and sets the shortest possible duration, while float is the slack a task has before it delays the project. Activities on the critical path have zero float.
The AIA Contract Suite
Contracts are the heart of PjM. The AIA documents are grouped by relationship: the letter tells you who is agreeing with whom.
Letter = relationship: B = owner-architect, A = owner-contractor, C = architect-consultant, G = forms.
The is the owner-architect agreement; the (stipulated sum) and (cost plus a fee with a ) are owner-contractor agreements; the General Conditions govern the whole construction relationship; and the retains the architect’s consultants. Consultant agreements should flow down from the prime agreement so scope, standard of care, and insurance align.
Project Execution & Scope
Execution means keeping the project on scope, schedule, and budget. Scope creep — the gradual, uncontrolled growth of work without matching fee or time — is the classic profit killer; it is controlled with a clear scope definition and written additional-services authorizations. The PM also monitors the construction budget, manages communication, and documents decisions in meeting minutes that protect the firm if disputes arise.
Project Quality Control
Quality assurance is the proactive process meant to prevent defects; quality control is the checking that catches them in the deliverables. A QC plan covers drawing coordination, code review, consultant coordination, and constructability review — confirming the design can actually be built — to cut RFIs and change orders later.
Checkpoint · Division 2 · Project Management
Question 1 of 10
An owner wants the lowest possible competitive construction price and is comfortable with a longer overall timeline. Which delivery method is generally most likely to produce the lowest bid price?
3 · Programming & Analysis (PA)
75 items · 3 hr.PA is the front of a project — analyzing the site and context, applying zoning and codes, and turning the owner’s needs into a building program. The heaviest section is Building Analysis & Programming (37–43%).[7]
Environmental & Contextual Conditions
A site has opportunities and constraints. Climate (sun, wind, temperature, rainfall), topography and soils, drainage, vegetation, views, and the surrounding context all shape design.
Solar orientationmanages daylight and heat gain, and a building’s microclimate is the local climate created by terrain, water, and neighbors. Sustainable analysis seeks the best on-site use of these resources.
Zoning, Codes & Land Use
controls what can be built where — use, density, height, , , lot coverage, and parking. FAR caps building bulk: a FAR of 2.0 on a 10,000-square-foot lot permits up to 20,000 square feet of floor area. An easement grants others a right to use part of a site (for utilities or access), restricting what an owner can build there.
Site Analysis
Site analysis studies a site’s physical, legal, and environmental conditions. A survey establishes legal boundaries; a topographic survey shows contour lines (points of equal elevation).
Closely spaced contours mean steep slopes; widely spaced contours mean flat ground — guiding grading, drainage, and where to place the building. A geotechnical (soils) report gives bearing capacity and the water table, which drive foundation choices.
Building Programming & Analysis
Programming defines the project’s goals, spaces, relationships, and constraints before design. The problem-seeking method (Peña) separates the problem from the solution through five steps: establish goals, collect and analyze facts, uncover concepts, determine needs, and state the problem. The owner is the primary source of goals.
| Concept | What it means |
|---|---|
| Net (assignable) area | Usable program space, excluding walls and circulation |
| Gross area | Total floor area to the outside of exterior walls |
| Efficiency ratio | Net / gross — typically ~60-80%; how much building to deliver the program |
| Adjacency diagram | Bubbles showing which spaces should be near, connected, or separated |
| Stacking / blocking | Distributing program vertically (stacking) and within a floor (blocking) |
| Pro forma | A financial projection testing whether the development is feasible |
Checkpoint · Division 3 · Programming & Analysis
Question 1 of 10
In the problem-seeking method, who is the primary source of the goals an architect records during programming?
4 · Project Planning & Design (PPD)
100 items · 4 hr 5 min — a big division. PPD is schematic design through design development: applying codes, choosing systems, and integrating everything into a coherent design. The heaviest section is Project Integration of Program & Systems (32–38%), and codes plus systems make up most of the rest.[8]
Codes: Occupancy, Area & Egress
The building code starts with two classifications. groups buildings by use and risk (Assembly, Business, Mercantile, Residential, and more), and (Type I–V) classifies them by the fire resistance and combustibility of the structure. Together they set allowable area and height, which sprinklers commonly increase.[12]
is the path to safety. It has three parts:
- 1. Exit AccessThe path leading to an exit — the corridor, aisle, or room travel to reach a protected route.
- 2. ExitThe protected portion — an enclosed exit stair, an exit passageway, or an exterior door.
- 3. Exit DischargeFrom the exit to a public way — the route from the building to the street or safe open space.
All three must be continuous and maintained — occupant load sets the required width and number of exits.
The occupant load (floor area divided by an occupancy factor) sets the required exit width and number of exits — most spaces need at least two, separated so one event cannot block them all. Travel distance to an exit is capped by code and is usually extended in sprinklered buildings.
Structural Systems
A structure carries two kinds of force. The gravity load path sends dead loads (permanent weight) and live loads (occupants, furniture) from roof and floors through beams and columns to the foundation.
Lateral loads — wind and seismic — are resisted by shear walls, braced frames, or moment frames. Common materials each have a signature: steel spans far and erects fast, concrete is strong in compression and fire-resistant, masonry is durable in compression, and wood is light and renewable but combustible.
Building Systems & Envelope
Passive strategies use form, orientation, mass, and shading to manage comfort with little energy; active systems (HVAC) condition the space mechanically — a variable-air-volume (VAV) system saves energy by varying airflow to each zone. The thermal envelope separates conditioned space from outside, controlling heat with insulation (R-value, higher is better) and glazing (U-factor, lower is better), continuous air barriers, and a vapor retarder placed to keep moisture from condensing inside the wall.
Sustainability, Cost & Integration
Sustainable design reduces environmental impact across site, energy, water, materials, and indoor environment; certifies projects by points. compares options by total cost of ownership — initial plus operating, maintenance, and replacement — not first cost alone. The integration section is the largest: it is about making program, systems, codes, and context work together in one design, balanced against the budget.
Checkpoint · Division 4 · Project Planning & Design
Question 1 of 10
What is the primary objective of the means of egress requirements in the building code?
5 · Project Development & Documentation (PDD)
100 items · 4 hr 5 min — the other big division. PDD turns the design into buildable documents and details. Its two largest sections, nearly tied, are Integration of Materials & Systems (31–37%) and Construction Documentation (32–38%).[9]
Construction Documents
Construction documents define the work well enough to permit, bid, and build it. They split cleanly: drawings show quantity, location, and dimension; the and its specifications describe quality, materials, and workmanship. The two are complementary — what one requires is binding as if required by all, and the architect interprets any conflict.
| Drawings | Specifications | |
|---|---|---|
| Answer | Where, how much, what size | What quality, which material, how installed |
| Examples | Plans, sections, details, schedules | Product data, standards, workmanship |
| Organized by | Sheet type and discipline | CSI MasterFormat divisions |
Project Manual & Specifications
Specifications are organized by (by work result) and each section follows SectionFormat: Part 1 General, Part 2 Products, Part 3 Execution. Methods of specifying shift control and risk: prescriptive (descriptive or proprietary) names exact products and methods, while performance states the required result and lets the contractor choose how to meet it. A reference-standard spec cites an industry standard like ASTM to stay concise.
| Method | How it works | Who controls the choice |
|---|---|---|
| Descriptive | Describes required properties without naming a product | Architect |
| Performance | States the result; contractor selects the means | Contractor |
| Reference standard | Requires compliance with an industry standard | The standard |
| Proprietary | Names a specific product (open with 'or-equal', or closed) | Architect |
Detailing & Material Integration
Good detailing controls four things at the envelope: water, air, vapor, and heat. Flashing directs water away from joints; a water-resistive barrier drains incidental water out through weep holes; continuous air and vapor barriers stop leakage and condensation; and breaking thermal bridges preserves the insulation’s value. Details must also accommodate movement — from temperature, moisture, and structural deflection — using control and expansion joints so finishes do not crack.
Codes & Cost in Documentation
The documents must satisfy the IBCand specialty codes, and a coordinated set keeps architectural, structural, and MEP drawings in agreement so the building can be built without clashes. PDD’s smallest section is construction cost estimates (2–8%) — by this stage the estimate is mainly checked for alignment with the developed design.[9]
Checkpoint · Division 5 · Project Development & Documentation
Question 1 of 10
During documentation, an architect selects a 'smart' (variable-permeance) vapor retarder for a wall assembly. What characteristic distinguishes this product from a standard polyethylene sheet?
6 · Construction & Evaluation (CE)
75 items · 3 hr.CE covers bidding and the architect’s role during construction. Its two largest sections are nearly tied: Construction Observation (32–38%) and Administrative Procedures & Protocols (32–38%).[10]
Preconstruction & Bidding
Before construction, the owner chooses a that sets who holds which contracts and how risk is shared.
| Method | How it works | Key trait |
|---|---|---|
| Design-bid-build (DBB) | Owner contracts architect, then contractor separately | Traditional; owner control; sequential, slower |
| Design-build (DB) | One entity provides design and construction | Single point of responsibility; fast; less owner control |
| CM at risk (CMc) | CM advises early, then holds the work at a GMP | Early cost/constructability input; overlaps design and build |
| CM agency | CM advises the owner; owner holds trade contracts | CM is the owner's adviser, not at financial risk |
| Integrated project delivery (IPD) | Owner, architect, contractor share one contract | Shared risk and reward; collaborative |
In bidding, the work is priced through competitive bids (open or selective) or negotiation. Bonds protect the owner: a bid bond guarantees the winner will sign, a performance bond guarantees completion, and a payment bond guarantees subcontractors and suppliers are paid (protecting against mechanic’s liens). An changes the bidding documents before the contract is signed.
Construction Administration & Observation
During construction the architect provides — but the scope of that role is heavily tested and frequently misunderstood. The architect observes the work at appropriate intervals to judge general conformance; the architect does notsupervise or control the contractor’s means, methods, sequences, or site safety— those are solely the contractor’s responsibility.
Submittals, Payments & Changes
Submittals (shop drawings, product data, samples) are reviewed by the architect only for conformance with the design intent— not for dimensions or quantities, which remain the contractor’s responsibility. An is the contractor’s formal question; the architect answers with an interpretation consistent with the documents.
Payment follows the : the contractor submits an Application for Payment (G702), the architect reviews and observes, then certifies the amount due less .
- 1. Schedule of Values (G703)The contract sum is divided among the parts of the work — the basis for measuring progress.
- 2. Application for Payment (G702)The contractor requests payment for completed work and stored materials each period.
- 3. Architect Reviews & ObservesThe architect compares the application against observed progress and the documents.
- 4. Certificate for PaymentThe architect certifies the amount due (less retainage); the owner pays the contractor.
- 5. Substantial → Final PaymentMost funds release at substantial completion; retainage releases at final completion.
The architect certifies payment based on observation — not a guarantee that every detail is perfect.
Changing the work is one of the most-tested distinctions on the whole exam:
Who must agree determines which instrument you use. This distinction is one of the most-tested ideas in Construction & Evaluation.
A CCD is the tool when the parties cannot yet agree on price — it later resolves into a change order.
Project Closeout & Evaluation
Two milestones end a project. is when the owner can occupy the work for its intended use — it starts warranties and triggers the ; is when everything, including the punch list, is done, releasing final payment.
- Owner can occupy/use for intended purpose
- Warranties begin
- Punch list issued; retainage reduced
- Documented on AIA G704
- All work, including punch list, complete
- Closeout documents submitted
- Final payment and remaining retainage released
- Consent of surety obtained
Substantial completion is the pivotal date — it starts warranties and shifts use to the owner.
Closeout also includes record (as-built) drawings, operation and maintenance manuals, warranties, lien releases, the , and often a to learn how the building actually performs.
Checkpoint · Division 6 · Construction & Evaluation
Question 1 of 10
During the preconstruction phase, what is the primary value the architect and contractor provide to the owner through preconstruction services?
How to Use This Study Guide
The ARE is six exams, not one, so treat each division as its own campaign. Study guides map the content; pair this one with the official NCARB ARE 5.0 Handbook and practice exams, the AIA contract documents, and the building code. With 2024 pass rates ranging from about 47% to 61%, steady, division-targeted practice is what separates a pass from a retake.[4]
- 1
Pick one division
Work a single division at a time — many candidates pair PPD and PDD because their content overlaps.
- 2
Read it section by section
Lead with the heaviest sections (the percentages tell you where the items are).
- 3
Take the checkpoint
The quick check at the end of each division exposes what didn't stick.
- 4
Drill the gaps, then sit it
Send weak areas into the free practice questions and flashcards, then schedule that division.
ARE 5.0 Concept Questions
Common ARE 5.0 concepts the exam tests — at least one per division. Tap any card for a short, exam-ready answer backed by an official source (NCARB, the AIA, the ICC, ADA.gov, the USGBC), then test yourself on them as flashcards.
ARE 5.0 Glossary
Quick definitions for the terms you’ll see most across the six ARE 5.0 divisions:
- Addendum
- A written change or clarification to the bidding documents issued to all bidders before the contract is signed.
- AIA A101
- The standard owner-contractor agreement where the basis of payment is a stipulated (lump) sum — a fixed price for the defined work.
- AIA A102
- An owner-contractor agreement where payment is the cost of the work plus a fee, with a guaranteed maximum price (GMP) that caps the owner's cost.
- AIA A201
- The General Conditions of the Contract for Construction — the 'rulebook' defining the duties of owner, contractor, and architect. It is incorporated by reference into most AIA owner-contractor agreements.
- AIA B101
- The standard owner-architect agreement. It defines the architect's basic services by phase, the fee, and the responsibilities of each party.
- AIA C401
- The standard architect-consultant agreement, by which the architect retains engineers and specialists; its terms should flow down from the owner-architect agreement.
- ASI
- An Architect's Supplemental Instruction — a minor change in the work consistent with the documents that does not affect the contract sum or time.
- Certificate of occupancy
- The building official's authorization that a building complies with code and is safe to occupy for its intended use.
- Change order
- A written contract modification, signed by owner, contractor, and architect, that changes the contract sum, time, or scope — all three parties agree.
- Construction administration
- The architect's services during construction — site observation, submittal review, RFIs, payment certification, and change management.
- Construction change directive
- An owner- and architect-directed change in the work issued without the contractor's agreement on cost or time; later resolved into a change order.
- Construction type
- The code classification (Type I through V) of a building by the fire resistance and combustibility of its structure; it interacts with occupancy to set allowable area and height.
- CSI MasterFormat
- The CSI standard that organizes specifications into numbered divisions by work result (for example, Division 03 Concrete, 09 Finishes).
- Efficiency ratio
- Net assignable (usable) area divided by gross area. It estimates how much building must be built to deliver the required program; typical values range from about 60 to 80 percent.
- Egress
- The continuous path of exit travel from any point in a building to a public way, made up of the exit access, the exit, and the exit discharge.
- FAR
- Floor area ratio — the ratio of a building's total floor area to its lot area. A FAR of 2.0 on a 10,000-square-foot lot allows up to 20,000 square feet.
- Final completion
- When all work, including punch-list items, is finished per the contract documents — triggering final payment and release of remaining retainage.
- Guaranteed maximum price
- A GMP is the most a contractor can charge; the owner pays actual costs plus a fee up to the cap, with savings below it often shared.
- LEED
- Leadership in Energy and Environmental Design — the U.S. Green Building Council's green-building rating system (Certified, Silver, Gold, Platinum).
- Life-cycle cost
- The total cost of a system or material over its life — initial cost plus operating, maintenance, and replacement costs — used to compare design options.
- Net multiplier
- Net operating revenue divided by direct (project) labor. It measures how much revenue each dollar of billable labor generates; a value around 3.0 is common.
- Occupancy classification
- The building code's categorization of a building by use and risk (such as Assembly, Business, Residential), driving allowable area, height, and egress.
- Overhead rate
- Total indirect cost divided by direct labor. The break-even rate equals 1.0 plus the overhead rate — the multiplier at which the firm covers costs but earns no profit.
- Post-occupancy evaluation
- An assessment of how a completed building performs in use — comfort, function, energy, satisfaction — to inform operations and future design.
- Pro forma
- A financial projection for a development showing estimated costs, income, and return; used to test whether a project is feasible.
- Project delivery method
- How an owner organizes design and construction — design-bid-build, design-build, CM at risk, CM agency, or integrated project delivery (IPD).
- Project manual
- The bound volume containing bidding requirements, contract conditions, and specifications — everything written that is not a drawing.
- Punch list
- The list of incomplete or deficient items the contractor must correct near the end of construction, prepared around substantial completion.
- Retainage
- A percentage (often 5 to 10 percent) withheld from each payment until the work is satisfactorily complete, giving the owner leverage to ensure completion.
- RFI
- A request for information — the contractor's formal written question asking the architect to clarify the contract documents during construction.
- Schedule of values
- A breakdown of the contract sum allocated to each portion of the work (AIA G703). It is the basis for reviewing the contractor's payment applications.
- Setback
- The minimum required distance between a building and a property line, established by zoning to provide light, air, and separation.
- Shop drawing
- A detailed fabrication or installation drawing prepared by the contractor or fabricator. The architect reviews it for conformance, not for dimensions or quantities.
- Standard of care
- The level of skill and diligence a reasonably prudent architect would exercise under similar circumstances. It is the legal benchmark for professional negligence — it requires competence, not perfection.
- Submittal
- Contractor-provided shop drawings, product data, or samples submitted for the architect's review for conformance with the design intent.
- Substantial completion
- The stage when the work is sufficiently complete for the owner to occupy or use it for its intended purpose. It starts warranties and triggers the punch list (AIA G704).
- Utilization rate
- Billable (direct) labor divided by total labor, also called the chargeable ratio. Higher utilization generally means more profit.
- Zoning
- Local land-use regulation controlling what can be built where — permitted uses, density, height, setbacks, lot coverage, and parking.
Free ARE 5.0 Study Materials & Resources
Everything you need to prepare for the ARE 5.0 is free here — no paywall, no sign-up. This guide is the foundation; pair it with the rest of our free ARE 5.0 study materials for active recall, timed practice, and last-minute review:
- ARE 5.0 Practice Test — exam-style questions across all six divisions, with explanations.
- ARE 5.0 Flashcards — active-recall decks for the AIA contracts, code rules, and high-yield concepts.
ARE 5.0 Study Guide FAQ
The six ARE 5.0 divisions are Practice Management (PcM), Project Management (PjM), Programming & Analysis (PA), Project Planning & Design (PPD), Project Development & Documentation (PDD), and Construction & Evaluation (CE). Each is a separate exam you schedule, pay for, and pass on its own, in any order you choose. You must pass all six to be ARE complete.
Item counts and times vary by division: Practice Management has 65 items (2 hr 40 min testing), Project Management 75 (3 hr), Programming & Analysis 75 (3 hr), Project Planning & Design 100 (4 hr 5 min), Project Development & Documentation 100 (4 hr 5 min), and Construction & Evaluation 75 (3 hr). Each division also includes flexible break time and two case studies, for 490 items total across the exam.
Each ARE 5.0 division is graded pass/fail against a minimum passing score, called a cut score, that represents entry-level competence. NCARB does not publish a fixed passing percentage — the cut score is set per division by a standard-setting process. Scoring is division-wide, so strong content areas can offset weaker ones.
It is demanding: six long appointments that blend recall with applied judgment. NCARB's 2024 pass rates ranged from about 47% (Project Planning & Design) to 61% (Programming & Analysis and Construction & Evaluation), with an overall pass rate near 55%. Most candidates spend many months passing all six divisions.
You can take the six divisions in any order. NCARB arranges them in the order of a project's life, and many candidates start with the division closest to their day-to-day work or pair related divisions, such as taking Project Planning & Design (PPD) and Project Development & Documentation (PDD) close together because their content overlaps.
Work through the six divisions one at a time, focusing on the heaviest content sections within each. After each division, take the checkpoint quiz to find gaps, then drill that division with our free ARE 5.0 practice questions and flashcards, and revisit flagged sections before your appointment.
Yes — the full guide, the checkpoints, the glossary, the practice questions, and the flashcards are 100% free with no account required.
High-yield, cross-division content includes the AIA contract documents (B101, A101/A102, A201, C401), the design phases (SD, DD, CD) and construction administration, building and zoning code basics (occupancy, construction type, egress, FAR), firm finances, and the difference between a change order, a construction change directive, and a minor change.
References
- 1.National Council of Architectural Registration Boards. “Your Guide to ARE 5.0 (ARE Booklet).” NCARB.org. ↑
- 2.National Council of Architectural Registration Boards. “How ARE 5.0 is Scored.” NCARB.org. ↑
- 3.National Council of Architectural Registration Boards. “ARE 5.0 Format & Question Types.” NCARB.org. ↑
- 4.National Council of Architectural Registration Boards. “ARE 5.0 Pass Rates.” NCARB.org. ↑
- 5.National Council of Architectural Registration Boards. “Practice Management (PcM) — Exam Content.” NCARB.org. ↑
- 6.National Council of Architectural Registration Boards. “Project Management (PjM) — Exam Content.” NCARB.org. ↑
- 7.National Council of Architectural Registration Boards. “Programming & Analysis (PA) — Exam Content.” NCARB.org. ↑
- 8.National Council of Architectural Registration Boards. “Project Planning & Design (PPD) — Exam Content.” NCARB.org. ↑
- 9.National Council of Architectural Registration Boards. “Project Development & Documentation (PDD) — Exam Content.” NCARB.org. ↑
- 10.National Council of Architectural Registration Boards. “Construction & Evaluation (CE) — Exam Content.” NCARB.org. ↑
- 11.The American Institute of Architects. “AIA Contract Documents — Document Families.” AIA Contract Documents. ↑
- 12.International Code Council. “International Building Code (IBC).” ICC (codes.iccsafe.org). ↑
- 13.U.S. Department of Justice. “2010 ADA Standards for Accessible Design.” ADA.gov. ↑
- 14.National Council of Architectural Registration Boards. “ARE 5.0 Fees.” NCARB.org. ↑
Sources for the concept answers
Every answer in the ARE 5.0 concept questions above is drawn from an official primary source:
- The American Institute of Architects. “AIA Contract Documents — A201 General Conditions.” AIA Contract Documents.
- U.S. Green Building Council. “LEED Rating System.” USGBC.org.

Career Employer
Career Employer is the ultimate resource to help you get started working the job of your dreams. We cover topics from general career information, career searching, exam preparation with free study materials, career interviewing, and becoming successful in your career of choice.
All PostsCareer Employer’s Editorial Process
Here at Career Employer, we focus a lot on providing factually accurate information that is always up to date. We strive to provide correct information using strict editorial processes, article editing, and fact-checking for all of the information found on our website. We only utilize trustworthy and relevant resources. To find out more, make sure to read our full editorial process page here.
