Click Study Flashcards above to open the flashcard hub — hundreds of PMP cards you can flip, match, type, or quiz yourself on. Every card is drawn from PMI’s three official domains, so you study exactly what the exam tests.[1] Pair them with our free practice test and study guide.
PMP Flashcard Study Modes
Flip mode lets you read a term, think, and turn the card to check yourself. Match turns short fronts like Lag and Lead into a timed pairing game. Type shows the definition and asks you to produce the term, so a card such as Crashing has to come from memory. Quiz builds multiple-choice questions from the same cards.

Why Flashcards Work for the PMP
Process carries 50% of the exam and the deck’s 130 cards, the largest block by far. These are the scheduling, scope, and control terms that show up behind situational questions: the difference between Lag and Lead, what Crashing does to a schedule, and how a Baseline and a Milestone anchor performance measurement. Broader fronts like Project and Program sit here too.
People is weighted at 42% and holds 62 cards covering team formation, conflict, and communication vocabulary. You will drill a RACI chart and what each letter assigns, a Team charter and the Ground rules inside it, and bias terms such as Halo effect. Cards on Delegation, Co-location, and Compromising round out how a project manager works with a Stakeholder.
Business Environment is 8% of the exam and 36 cards, but the terms are precise and easy to confuse. Expect the Business case, the contrast in EEFs vs. OPAs, and the difference between a Directive PMO and a Supportive PMO. Financial fronts like Payback period, Value delivery, and Benefits owner also appear here.
Agile & Hybrid adds 52 cards of delivery vocabulary that cuts across the weighted domains. You get framework basics such as Scrum and Kanban, backlog structure through Epic, Theme, and User story, and flow measures like Velocity and WIP limit, plus the meaning of Agile itself as a mindset rather than a single method.
Foundations & Mindset is the smallest section at 24 cards and sets the frame for everything else. It covers the credential and its issuing body through PMP, PMI, and PMP eligibility, the role of a Sponsor, the purpose of the PMBOK Guide, and what Tailoring and the PMI mindset mean in practice, including the PDU.
The PMP is dense with terminology — earned-value formulas, agile roles and ceremonies, risk response strategies, conflict modes, and contract types.[2] Spaced flashcards are the most efficient way to keep it all fresh. Used alongside our practice test and study guide, they turn review time into measurable progress.
PMP Flashcards by Domain
The cards are organized by PMI’s three official domains, plus dedicated Agile & Hybrid and Foundations decks. Drill the highest-weighted domains first — Process and People make up 92% of the exam:[1]
| Domain / deck | Exam weight |
|---|---|
| Process | 50% |
| People | 42% |
| Business Environment | 8% |
| Agile & Hybrid | Cross-cutting (≈half of all questions) |
| Foundations & Mindset | Cross-cutting (exam facts & PMI mindset) |
How to Get the Most Out of These Flashcards
- Start with Process. At 50% of the exam and 130 cards, it is both the heaviest domain and the largest stack, so early passes there pay back across every question type.
- Type the confusable pairs. Drill Lag and Lead until the definitions produce the right word instantly, and do the same with Crashing so you do not swap it with schedule compression alternatives.
- Use Match for short People fronts. Terms like RACI chart and Halo effect pair quickly under time pressure, which builds the recall speed situational questions demand.
- Switch to the practice test once recall is clean. When Quiz stops surprising you across Process and People, move to full-length questions and use the study guide for anything that still slips.
- Keep a rotating cadence. Work one domain per session, then run a mixed Flip pass over all 304 cards so Agile & Hybrid and Foundations & Mindset stay warm.
PMP Flashcards FAQ
Hundreds of free PMP flashcards, organized across all three PMI domains — People, Process, and Business Environment — plus dedicated Agile & Hybrid and Foundations decks. They're free with no account required.
Yes. Flashcards use active recall — retrieving an answer from memory — which research shows is one of the most effective study methods, especially in short, spaced sessions. They're ideal for the PMP's heavy terminology: EVM formulas, agile roles, risk responses, and conflict modes.
All three ECO domains: People (servant leadership, Tuckman, conflict, stakeholders), Process (scope, schedule, earned value, quality, risk, procurement), and Business Environment (compliance, value, NPV/ROI), plus Agile & Hybrid (Scrum, Kanban) and exam Foundations.
Lead with the highest-weighted domains — Process (50%) and People (42%) — then Business Environment. Mix the modes: flip to learn, type to test recall, match for speed, and quiz to check yourself before a full practice test. Drill the EVM and agile decks until they're automatic.
Yes — 100% free, all four study modes, no paywall.
Yes. The cards follow PMI's current Examination Content Outline and PMBOK Guide. PMI launches an updated exam on July 9, 2026 that keeps the same three domains but rebalances the weights toward Business Environment — these cards cover all three domains, so they serve both versions.
PMP flashcard bank
All 304 cards, by topic
A reference copy of every card in this deck. Each answer stays hidden until you choose to show it. To study with Flip, Match, Type and Quiz modes and track what you have mastered, use Study Flashcards at the top of the page.
People (62)
- Servant leadership
Show answerHide answer
A leadership style where the project manager serves the team — removing impediments, providing what they need, and developing people — to enable a self-organizing, high-performing team.
- Tuckman ladder
Show answerHide answer
The team-development model: forming, storming, norming, performing, and adjourning.
- Forming (Tuckman)
Show answerHide answer
The first team stage: members come together, polite and uncertain; the leader provides direction.
- Storming (Tuckman)
Show answerHide answer
The stage where conflict surfaces as members assert ideas; the leader coaches and resolves conflict.
- Norming (Tuckman)
Show answerHide answer
The stage where norms and trust form and the team begins to work effectively together.
- Performing (Tuckman)
Show answerHide answer
The stage where the team is high-performing and largely self-organizing; the leader delegates.
- Adjourning (Tuckman)
Show answerHide answer
The final stage where work completes and the team disbands; recognize and release members.
- Emotional intelligence
Show answerHide answer
The ability to recognize and manage your own emotions and to read and influence others' emotions; the basis of leading people.
- Components of emotional intelligence
Show answerHide answer
Self-awareness, self-regulation, motivation, empathy, and social skill.
- RACI chart
Show answerHide answer
A responsibility assignment matrix marking who is Responsible, Accountable, Consulted, and Informed for each task.
- Responsible (RACI)
Show answerHide answer
The person who does the work to complete the task.
- Accountable (RACI)
Show answerHide answer
The single person who owns the outcome and signs off — exactly one per task.
- Consulted (RACI)
Show answerHide answer
Subject-matter experts whose two-way input is sought before a decision.
- Informed (RACI)
Show answerHide answer
People kept up to date one-way on progress and decisions.
- Conflict-resolution modes
Show answerHide answer
Collaborate, compromise, smooth (accommodate), force (direct), and withdraw (avoid).
- Collaborating / problem-solving
Show answerHide answer
Working together to a win-win that addresses everyone's needs — the most effective, durable conflict mode and the usual PMP answer.
- Compromising
Show answerHide answer
Each party gives up something for a partial win — a lose-lose middle ground.
- Smoothing / accommodating
Show answerHide answer
Emphasizing agreement over differences and conceding your position; a temporary fix.
- Forcing / directing
Show answerHide answer
Pushing one viewpoint at others' expense — a fast win-lose outcome that breeds resentment.
- Withdrawing / avoiding
Show answerHide answer
Retreating from or postponing a conflict, leaving it unresolved; can buy a cooling-off period.
- Best conflict mode on the PMP
Show answerHide answer
Collaborating (problem-solving / confronting) — address the root cause and build a win-win.
- Stakeholder
Show answerHide answer
Any individual, group, or organization that can affect, be affected by, or perceive itself affected by the project.
- Stakeholder engagement steps
Show answerHide answer
Identify stakeholders, analyze (power/interest/influence), plan engagement, then manage and monitor engagement.
- Power/interest grid
Show answerHide answer
A tool classifying stakeholders by power and interest to decide how closely to engage each one.
- Manage closely (power/interest)
Show answerHide answer
High power, high interest — partner with and actively involve them.
- Keep satisfied (power/interest)
Show answerHide answer
High power, low interest — meet their needs without overloading them.
- Keep informed (power/interest)
Show answerHide answer
Low power, high interest — communicate often; they care about the project.
- Monitor (power/interest)
Show answerHide answer
Low power, low interest — minimal effort.
- Team charter
Show answerHide answer
A document the team creates defining its values, agreements, ground rules, and how it will operate.
- Ground rules
Show answerHide answer
Explicit, team-agreed expectations for behavior and collaboration, enforced by the whole team.
- Self-organizing team
Show answerHide answer
A team that decides internally how to accomplish its work rather than being directed task-by-task.
- Virtual team
Show answerHide answer
A team whose members work from different locations; needs extra-clear communication and tools.
- Motivation theory: Maslow
Show answerHide answer
Maslow's hierarchy: physiological, safety, social, esteem, and self-actualization needs.
- Motivation theory: Herzberg
Show answerHide answer
Hygiene factors (e.g., pay, conditions) prevent dissatisfaction; motivators (e.g., achievement, recognition) drive satisfaction.
- Theory X vs. Theory Y
Show answerHide answer
Theory X assumes people dislike work and need control; Theory Y assumes people are self-motivated and seek responsibility.
- Coaching vs. mentoring
Show answerHide answer
Coaching builds specific skills/performance now; mentoring is a longer-term relationship developing the whole person.
- Negotiation (project agreements)
Show answerHide answer
Reaching agreement through good-faith discussion; aim for win-win outcomes that preserve the relationship.
- Active listening
Show answerHide answer
Fully concentrating on, understanding, and responding to a speaker to build shared understanding and trust.
- Empowering the team
Show answerHide answer
Delegating authority and decisions to the team so members own outcomes — central to servant leadership.
- Removing impediments
Show answerHide answer
A servant-leader duty: clearing blockers and obstacles so the team can keep delivering value.
- Building shared understanding
Show answerHide answer
Ensuring stakeholders and the team have a common view of goals, scope, and success.
- Leadership vs. management
Show answerHide answer
Leadership inspires and aligns people toward a vision; management organizes and controls work and resources.
- Halo effect
Show answerHide answer
Assuming someone good at one thing will be good at another (e.g., promoting a strong engineer to manager).
- Servant-leader behaviors
Show answerHide answer
Listen, empathize, coach, facilitate, remove impediments, and develop the team's autonomy.
- Team performance via EI
Show answerHide answer
Use emotional intelligence to read morale, defuse tension, and motivate the team.
- Source of most conflict
Show answerHide answer
Schedules, priorities, and resources cause more project conflict than personality clashes.
- When to escalate conflict
Show answerHide answer
Only after collaborative resolution genuinely fails or the issue is beyond your authority.
- Delegation
Show answerHide answer
Entrusting authority and decisions to a capable team while staying available to remove blockers.
- Brainstorming
Show answerHide answer
A group technique to generate many ideas without early judgment, used in planning and risk ID.
- Nominal group technique
Show answerHide answer
Brainstorming plus voting to rank ideas by priority.
- Delphi technique
Show answerHide answer
Anonymous rounds of expert input with feedback to build consensus and reduce bias.
- Multicriteria decision analysis
Show answerHide answer
Scoring options against weighted criteria to choose objectively.
- Conflict is...
Show answerHide answer
Inevitable and can be healthy when managed openly; the PM addresses it early.
- Recognition and rewards
Show answerHide answer
Reinforce desired behavior; should be timely, fair, and valued by the recipient.
- Co-location
Show answerHide answer
Placing the team in one physical space (e.g., a war room) to boost communication.
- Tight matrix
Show answerHide answer
Co-location of project team members; unrelated to organizational structure type.
- Stakeholder register
Show answerHide answer
A document listing stakeholders with their interests, influence, and engagement needs.
- Salience model
Show answerHide answer
Classifies stakeholders by power, urgency, and legitimacy.
- Engagement assessment matrix
Show answerHide answer
Compares current vs. desired stakeholder engagement (unaware → leading).
- Forming the team charter
Show answerHide answer
The team itself creates it, which builds buy-in and ownership of the rules.
- Building trust
Show answerHide answer
Be transparent, consistent, and reliable; trust is the foundation of a high-performing team.
- Negotiation BATNA
Show answerHide answer
Best Alternative To a Negotiated Agreement — your fallback if talks fail; strengthens your position.
Process (130)
- Project
Show answerHide answer
A temporary endeavor undertaken to create a unique product, service, or result, with a definite start and end.
- Operations vs. project
Show answerHide answer
Operations are ongoing and repetitive; a project is temporary and produces a unique result.
- Program
Show answerHide answer
A group of related projects managed together to gain benefits not available from managing them separately.
- Portfolio
Show answerHide answer
A collection of projects, programs, and operations managed as a group to meet strategic objectives.
- Project charter
Show answerHide answer
The document that formally authorizes the project, names the PM, and grants authority to use resources.
- Integration management
Show answerHide answer
The PM's unique work of coordinating all the subsidiary plans and processes into one coherent whole.
- Project management plan
Show answerHide answer
The approved, integrated document defining how the project is executed, monitored, and closed.
- Work breakdown structure (WBS)
Show answerHide answer
A hierarchical decomposition of the total project scope into deliverables and work packages.
- Work package
Show answerHide answer
The lowest level of the WBS — the unit you estimate, schedule, and assign.
- 100% rule (WBS)
Show answerHide answer
The WBS captures all the project work and only the project work; nothing outside it is in scope.
- Scope baseline
Show answerHide answer
The approved scope statement, WBS, and WBS dictionary used to measure scope performance.
- Scope creep
Show answerHide answer
Uncontrolled changes or additions to scope without going through change control.
- Gold plating
Show answerHide answer
Adding features or work the customer didn't request — wasted effort and added risk.
- Progressive elaboration
Show answerHide answer
Adding detail to plans as more is known; healthy, unlike uncontrolled scope change.
- Requirements traceability matrix
Show answerHide answer
A grid linking each requirement to its origin and deliverable to ensure all are met.
- Integrated change control
Show answerHide answer
The single process for reviewing, approving, and managing changes across the project.
- Change control board (CCB)
Show answerHide answer
A chartered group that reviews and approves or rejects requested changes.
- Change request
Show answerHide answer
A formal proposal to modify a document, deliverable, or baseline; routed through change control.
- Baseline
Show answerHide answer
An approved version of scope, schedule, or cost against which performance is measured; changed only via change control.
- Critical path
Show answerHide answer
The longest path of dependent activities through the schedule; the shortest time to finish the project.
- Float / slack
Show answerHide answer
How long an activity can be delayed without delaying a later milestone.
- Total float
Show answerHide answer
Delay an activity can absorb without delaying the project end date.
- Free float
Show answerHide answer
Delay an activity can absorb without delaying the next (successor) activity.
- Critical-path activities float
Show answerHide answer
Zero total float — any delay delays the whole project.
- Crashing
Show answerHide answer
Compressing the schedule by adding resources to critical-path activities; increases cost.
- Fast tracking
Show answerHide answer
Compressing the schedule by running activities in parallel that were sequential; increases risk.
- Lead
Show answerHide answer
An overlap that lets a successor activity start before its predecessor finishes.
- Lag
Show answerHide answer
A required delay between a predecessor and a successor activity.
- Milestone
Show answerHide answer
A significant point or event in the project with zero duration.
- Schedule network diagram
Show answerHide answer
A visual of activities and their logical dependencies used to find the critical path.
- Cost baseline
Show answerHide answer
The approved, time-phased budget (excluding management reserve) used to measure cost performance.
- Management reserve
Show answerHide answer
Budget held for unknown-unknowns; not in the cost baseline; needs management approval to use.
- Contingency reserve
Show answerHide answer
Budget for identified (known) risks; part of the cost baseline.
- Earned value management (EVM)
Show answerHide answer
An integrated method combining scope, schedule, and cost to measure and forecast performance.
- Planned value (PV)
Show answerHide answer
The authorized budget for the work scheduled to be done by a given date.
- Earned value (EV)
Show answerHide answer
The budgeted cost of the work actually completed by a given date.
- Actual cost (AC)
Show answerHide answer
The real cost incurred for the work completed by a given date.
- Budget at completion (BAC)
Show answerHide answer
The total authorized budget for the project's planned work.
- Cost variance (CV)
Show answerHide answer
CV = EV − AC. Negative means over budget; positive means under budget.
- Schedule variance (SV)
Show answerHide answer
SV = EV − PV. Negative means behind schedule; positive means ahead.
- Cost performance index (CPI)
Show answerHide answer
CPI = EV ÷ AC. Greater than 1 is under budget; less than 1 is over budget.
- Schedule performance index (SPI)
Show answerHide answer
SPI = EV ÷ PV. Greater than 1 is ahead of schedule; less than 1 is behind.
- Estimate at completion (EAC)
Show answerHide answer
Forecast total cost. When current performance continues, EAC = BAC ÷ CPI.
- Estimate to complete (ETC)
Show answerHide answer
The expected cost to finish the remaining work; ETC = EAC − AC.
- Variance at completion (VAC)
Show answerHide answer
How far off budget the project will finish; VAC = BAC − EAC.
- To-complete performance index (TCPI)
Show answerHide answer
The cost efficiency needed on remaining work to hit the budget; TCPI = (BAC − EV) ÷ (BAC − AC).
- Reading CPI / SPI
Show answerHide answer
A value above 1 is favorable; exactly 1 is on plan; below 1 is unfavorable.
- EVM memory aid
Show answerHide answer
Every formula starts with EV; divide for an index (CPI, SPI), subtract for a variance (CV, SV).
- Quality vs. grade
Show answerHide answer
Quality is conformance to requirements; grade is a category of features. Low quality is always a problem; low grade may be acceptable.
- Quality assurance (manage quality)
Show answerHide answer
Process-focused activities that build confidence the project will meet quality requirements.
- Quality control (control quality)
Show answerHide answer
Product-focused activities that verify deliverables meet requirements.
- Cost of quality (COQ)
Show answerHide answer
The total cost of conformance (prevention, appraisal) plus non-conformance (failure) costs.
- Prevention vs. inspection
Show answerHide answer
Quality is built in (prevention), not inspected in; prevention is cheaper than fixing defects later.
- Cause-and-effect (Ishikawa) diagram
Show answerHide answer
A fishbone diagram that traces a problem to its potential root causes.
- Pareto chart
Show answerHide answer
A bar chart ordering causes by frequency — the 80/20 rule highlights the vital few.
- Control chart
Show answerHide answer
A chart tracking a process over time against control limits to detect out-of-control variation.
- Risk
Show answerHide answer
An uncertain event or condition that, if it occurs, affects a project objective.
- Risk management process
Show answerHide answer
Plan, identify, perform qualitative analysis, perform quantitative analysis, plan responses, implement & monitor.
- Risk register
Show answerHide answer
The artifact recording identified risks with probability, impact, owner, and planned responses.
- Qualitative risk analysis
Show answerHide answer
Prioritizing risks by probability and impact, usually with a probability-and-impact matrix.
- Quantitative risk analysis
Show answerHide answer
Numerically modeling the combined effect of top risks on cost and schedule.
- Threat responses
Show answerHide answer
Avoid, transfer, mitigate, accept, or escalate.
- Opportunity responses
Show answerHide answer
Exploit, share, enhance, accept, or escalate.
- Avoid (threat)
Show answerHide answer
Eliminate the threat entirely, e.g., by changing the plan.
- Transfer (threat)
Show answerHide answer
Shift the threat's impact to a third party, e.g., insurance or a contract.
- Mitigate (threat)
Show answerHide answer
Reduce the probability or impact of the threat.
- Exploit (opportunity)
Show answerHide answer
Take action to make the opportunity certain to happen.
- Enhance (opportunity)
Show answerHide answer
Increase the probability or impact of an opportunity.
- Share (opportunity)
Show answerHide answer
Partner with a third party best able to capture the opportunity.
- Accept (risk)
Show answerHide answer
Take no proactive action; for threats, often hold a contingency reserve.
- Escalate (risk)
Show answerHide answer
Raise a risk outside the project's authority to the right level to own it.
- Secondary risk
Show answerHide answer
A new risk created by implementing a risk response.
- Residual risk
Show answerHide answer
The risk that remains after responses have been applied.
- Procurement
Show answerHide answer
Obtaining goods or services from outside the project team, governed by contracts.
- Fixed-price contract
Show answerHide answer
A set price for the work; the seller carries most of the cost risk.
- Cost-reimbursable contract
Show answerHide answer
Pays the seller's allowable costs plus a fee; the buyer carries more cost risk.
- Time and materials (T&M) contract
Show answerHide answer
Pays hourly/unit rates with no fixed total; cost risk is shared.
- Statement of work (SOW)
Show answerHide answer
A description of the procurement item detailed enough for sellers to bid and deliver.
- Make-or-buy decision
Show answerHide answer
Deciding whether to produce a deliverable in-house or procure it externally.
- Communications management
Show answerHide answer
Planning, creating, distributing, and managing project information to the right people.
- Communication channels formula
Show answerHide answer
Number of channels = n × (n − 1) ÷ 2, where n is the number of people.
- Push vs. pull communication
Show answerHide answer
Push sends info to recipients (email, reports); pull lets recipients retrieve it (portals, wikis).
- Lessons learned
Show answerHide answer
Knowledge gained during the project, recorded so future projects benefit; part of OPAs.
- Project closure
Show answerHide answer
Finalizing all activities, getting acceptance, releasing resources, and archiving documents.
- Methodology selection
Show answerHide answer
Choosing predictive, agile, or hybrid based on the project's certainty, change rate, and context.
- Project governance
Show answerHide answer
The framework of rules, roles, and decision rights guiding how a project is directed and controlled.
- Issue log
Show answerHide answer
A record of current problems (issues) that need resolution, with owners and status.
- Decision tree analysis
Show answerHide answer
A quantitative technique comparing options' expected monetary value under uncertainty.
- Expected monetary value (EMV)
Show answerHide answer
EMV = probability × impact; used to compare risky options.
- Three-point estimate (PERT)
Show answerHide answer
Estimate = (optimistic + 4 × most likely + pessimistic) ÷ 6, smoothing estimation uncertainty.
- Validate scope
Show answerHide answer
The buyer/customer formally accepts completed deliverables; about acceptance, not correctness.
- Control scope vs. validate scope
Show answerHide answer
Control scope monitors and manages scope changes; validate scope gets formal acceptance.
- Rolling wave planning
Show answerHide answer
Plan near-term work in detail and later work at a higher level, refining as you go.
- Analogous estimating
Show answerHide answer
Estimating using a similar past project; fast but less accurate (top-down).
- Parametric estimating
Show answerHide answer
Estimating using a statistical relationship (e.g., cost per unit) and known quantities.
- Bottom-up estimating
Show answerHide answer
Estimating each work package and rolling them up; accurate but time-consuming.
- Reserve analysis
Show answerHide answer
Determining contingency and management reserves for schedule and cost.
- Schedule compression
Show answerHide answer
Crashing (add resources, more cost) or fast-tracking (parallelize, more risk).
- Resource leveling
Show answerHide answer
Adjusting start/finish dates to balance resource demand; can extend the schedule.
- Resource smoothing
Show answerHide answer
Adjusting within float so resource use stays under a limit without changing the critical path.
- Finish-to-start (FS)
Show answerHide answer
The most common dependency: a successor can't start until its predecessor finishes.
- Mandatory dependency
Show answerHide answer
A hard logic dependency inherent to the work (e.g., build walls before roof).
- Discretionary dependency
Show answerHide answer
A preferred (soft) sequence based on best practice, not a hard requirement.
- Earned value: SV in time
Show answerHide answer
SV in dollars; SPI shows schedule efficiency as a ratio (EV ÷ PV).
- Quality audit
Show answerHide answer
A structured review to confirm the project follows quality policies and processes.
- Inspection
Show answerHide answer
Examining a deliverable to verify it conforms to requirements (a QC activity).
- Checklist
Show answerHide answer
A structured tool listing items to verify during quality control or risk identification.
- Histogram
Show answerHide answer
A bar chart showing the distribution of data, used in quality analysis.
- Scatter diagram
Show answerHide answer
A chart plotting two variables to reveal a relationship or correlation.
- Flowchart
Show answerHide answer
A diagram of process steps used to find quality problems or improvement points.
- Probability and impact matrix
Show answerHide answer
A grid ranking risks by their likelihood and effect to prioritize them.
- Risk categories (RBS)
Show answerHide answer
A risk breakdown structure groups risks (technical, external, organizational, PM).
- Risk owner
Show answerHide answer
The person accountable for monitoring a risk and carrying out its response.
- Watchlist
Show answerHide answer
Low-priority risks recorded for periodic review rather than active response.
- Trigger / warning sign
Show answerHide answer
An indicator that a risk is about to occur or has occurred.
- Sensitivity analysis (tornado)
Show answerHide answer
Shows which risks have the most potential impact on the objective.
- Monte Carlo simulation
Show answerHide answer
A quantitative technique modeling many outcomes to assess overall project risk.
- Bid documents
Show answerHide answer
RFP, RFQ, and IFB used to solicit seller proposals or quotes.
- Source selection criteria
Show answerHide answer
The factors used to evaluate and choose a seller (price, capability, etc.).
- Contract closure
Show answerHide answer
Confirming all contract work and terms are complete and formally closing the agreement.
- Force majeure
Show answerHide answer
A contract clause excusing performance due to extraordinary events beyond control.
- Communication methods
Show answerHide answer
Interactive (meetings/calls), push (email/reports), and pull (portals/wikis).
- Communication model
Show answerHide answer
Sender encodes, transmits through a medium with noise, receiver decodes and acknowledges.
- Stakeholder notification
Show answerHide answer
Keeping affected parties informed of decisions, issues, and resolutions.
- Project artifacts
Show answerHide answer
Documents and deliverables produced by the project (plans, logs, reports, registers).
- Knowledge transfer
Show answerHide answer
Sharing tacit and explicit knowledge across the team and into the organization.
- Phase gate / kill point
Show answerHide answer
A review at a phase boundary to decide whether to continue, change, or end the project.
- Configuration management
Show answerHide answer
Controlling versions of deliverables and documents to ensure consistency.
- Issue vs. risk
Show answerHide answer
A risk is a future uncertainty; an issue is a current problem already happening.
- Cost baseline excludes
Show answerHide answer
Management reserve (which is added for unknown-unknowns and needs approval to use).
Business Environment (36)
- Business environment domain
Show answerHide answer
Connects the project to the wider organization: compliance, value/benefits delivery, and organizational change.
- Business case
Show answerHide answer
The documented justification for a project — its need, options, costs, and expected benefits.
- Benefits realization
Show answerHide answer
Confirming a project's intended value and benefits are actually achieved, often after it closes.
- Benefits management plan
Show answerHide answer
The plan describing how and when a project's benefits will be delivered and measured.
- Value delivery
Show answerHide answer
Producing outcomes that meet stakeholder needs and create value, not just deliverables.
- Net present value (NPV)
Show answerHide answer
Future cash flows discounted to today minus the investment; a positive, higher NPV is better.
- Return on investment (ROI)
Show answerHide answer
The percentage gain from a project relative to its cost; higher is better.
- Payback period
Show answerHide answer
The time for a project's cumulative inflows to recover the initial investment; shorter is better.
- Benefit-cost ratio (BCR)
Show answerHide answer
Benefits divided by costs; greater than 1 means benefits exceed costs.
- Internal rate of return (IRR)
Show answerHide answer
The discount rate at which a project's NPV is zero; higher IRR is generally better.
- Choosing by NPV
Show answerHide answer
When projects cost the same, the higher NPV is the stronger financial choice.
- Compliance management
Show answerHide answer
Planning and managing adherence to laws, regulations, standards, and organizational policy.
- Treating compliance as risk
Show answerHide answer
Potential non-compliance is identified and handled like any other project risk.
- External environment changes
Show answerHide answer
New regulations, market shifts, or technology that the PM monitors and responds to via change control.
- Enterprise environmental factors (EEFs)
Show answerHide answer
Conditions outside the team's control — culture, market, regulations — that influence the project.
- Organizational process assets (OPAs)
Show answerHide answer
The organization's own plans, processes, policies, templates, and knowledge bases used on projects.
- EEFs vs. OPAs
Show answerHide answer
EEFs are external conditions you adapt to; OPAs are internal assets you use and add to.
- Organizational change management
Show answerHide answer
Preparing and supporting people to adopt a new way of working so project benefits stick.
- Project vs. product success
Show answerHide answer
A project can finish on time and on budget yet fail if the intended value never materializes.
- Strategic alignment
Show answerHide answer
Ensuring the project supports the organization's strategy and goals; reason to start or stop it.
- Organizational structures
Show answerHide answer
Functional, matrix (weak/balanced/strong), and projectized — they set the PM's authority level.
- PM authority by structure
Show answerHide answer
Lowest in functional, highest in projectized; matrix is in between by type.
- Project management office (PMO)
Show answerHide answer
An organizational body that standardizes and supports project governance; supportive, controlling, or directive.
- Regulatory compliance example
Show answerHide answer
A healthcare data project must meet privacy rules (e.g., HIPAA); compliance gaps are risks to address early.
- Compliance categories
Show answerHide answer
Legal/regulatory, safety, quality/standards, and organizational policy.
- Sustainability / ESG
Show answerHide answer
Considering environmental, social, and governance impacts in project decisions.
- Market & competitive changes
Show answerHide answer
External shifts the PM must assess for impact on scope, value, and viability.
- Continued business justification
Show answerHide answer
Periodically confirming the project still delivers value; if not, recommend stopping it.
- Value vs. output
Show answerHide answer
Delivering value means achieving outcomes and benefits, not merely producing deliverables.
- Benefits owner
Show answerHide answer
Often a business sponsor, accountable for realizing benefits after the project ends.
- Functional organization
Show answerHide answer
Staff grouped by specialty; the functional manager has authority, the PM little.
- Projectized organization
Show answerHide answer
The whole organization is structured around projects; the PM has high authority.
- Matrix organization
Show answerHide answer
Shares authority between functional and project managers (weak, balanced, or strong).
- Supportive PMO
Show answerHide answer
Provides templates, training, and lessons learned; low control.
- Controlling PMO
Show answerHide answer
Requires compliance with frameworks and methodologies; moderate control.
- Directive PMO
Show answerHide answer
Directly manages projects; high control.
Agile & Hybrid (52)
- Agile
Show answerHide answer
An iterative, change-driven approach that fixes time and cost and flexes scope by priority to deliver value early.
- Predictive (waterfall)
Show answerHide answer
A plan-driven approach that fixes scope up front; best for stable, well-understood work.
- Hybrid approach
Show answerHide answer
A delivery approach blending predictive and agile elements, tailored to the project.
- When agile fits
Show answerHide answer
High uncertainty, fast-changing requirements, and a need for early, frequent feedback.
- When predictive fits
Show answerHide answer
Stable, well-defined requirements with fixed scope and low expected change.
- Agile Manifesto values
Show answerHide answer
Individuals & interactions, working software, customer collaboration, and responding to change.
- Iteration / sprint
Show answerHide answer
A short, fixed-length timebox (often 1–4 weeks) producing a usable increment.
- Scrum
Show answerHide answer
An agile framework delivering work in sprints with set roles and ceremonies.
- Scrum roles
Show answerHide answer
Product owner, scrum master, and developers (the development team).
- Product owner
Show answerHide answer
Owns and orders the product backlog to maximize value; the voice of the customer.
- Scrum master
Show answerHide answer
A servant leader who facilitates Scrum, coaches the team, and removes impediments.
- Developers (Scrum)
Show answerHide answer
The cross-functional team members who build the increment each sprint.
- Scrum ceremonies
Show answerHide answer
Sprint planning, daily standup, sprint review, and sprint retrospective.
- Sprint planning
Show answerHide answer
The team selects backlog items it can complete and sets a sprint goal.
- Daily standup
Show answerHide answer
A short daily sync covering progress, plan, and impediments.
- Sprint review
Show answerHide answer
Demonstrating the increment to stakeholders to gather feedback.
- Sprint retrospective
Show answerHide answer
The team inspects how it worked and commits to improvements.
- Product backlog
Show answerHide answer
An ordered, evolving list of everything that might be needed in the product, owned by the product owner.
- Sprint backlog
Show answerHide answer
The set of backlog items the team commits to deliver in the current sprint.
- User story
Show answerHide answer
A short, user-centered requirement: 'As a [role], I want [goal] so that [benefit].'
- Definition of done
Show answerHide answer
The team's shared, explicit criteria for an increment to be considered complete.
- Velocity
Show answerHide answer
The amount of work a team completes per iteration, used to forecast future capacity.
- Story points
Show answerHide answer
A relative estimate of effort/complexity for a backlog item, not a time estimate.
- Minimum viable product (MVP)
Show answerHide answer
The smallest releasable product that delivers value and enables learning.
- Kanban
Show answerHide answer
An agile method that visualizes work and limits work in progress (WIP) to improve flow.
- WIP limit
Show answerHide answer
A cap on how many items can be in a workflow stage at once, to improve flow and surface bottlenecks.
- Kanban board
Show answerHide answer
A visual board showing work items moving through workflow columns.
- Scrum vs. Kanban
Show answerHide answer
Scrum is cadence- and commitment-based (sprints); Kanban is flow- and WIP-limit-based (continuous).
- Burndown chart
Show answerHide answer
A chart showing remaining work over time within a sprint or release.
- Burnup chart
Show answerHide answer
A chart showing completed work climbing toward total scope over time.
- Information radiator
Show answerHide answer
A highly visible display (e.g., board, charts) that broadcasts project status to everyone.
- Servant leader in agile
Show answerHide answer
The scrum master/PM facilitates and removes impediments rather than directing the team's tasks.
- Backlog refinement
Show answerHide answer
Ongoing work to add detail, estimates, and order to backlog items.
- Timeboxing
Show answerHide answer
Fixing a maximum duration for an activity to focus effort and force prioritization.
- Incremental delivery
Show answerHide answer
Releasing usable pieces of the product over time so value and feedback come early.
- Retrospective purpose
Show answerHide answer
Continuous improvement — the team identifies what to keep, drop, and try next.
- Iterative vs. incremental
Show answerHide answer
Iterative refines through repeated cycles; incremental delivers in usable pieces; agile uses both.
- Empirical process control
Show answerHide answer
Decisions based on observation and experimentation (transparency, inspection, adaptation).
- Three pillars of Scrum
Show answerHide answer
Transparency, inspection, and adaptation.
- Spike (agile)
Show answerHide answer
A timeboxed investigation to reduce uncertainty about an approach or estimate.
- Epic
Show answerHide answer
A large body of work that can be broken down into multiple user stories.
- Theme
Show answerHide answer
A group of related epics or stories aligned to a goal.
- Acceptance criteria
Show answerHide answer
Conditions a user story must meet to be accepted as done.
- INVEST (user stories)
Show answerHide answer
Good stories are Independent, Negotiable, Valuable, Estimable, Small, and Testable.
- Planning poker
Show answerHide answer
A consensus estimating game using relative story-point cards.
- Release planning
Show answerHide answer
Mapping which features/increments will be delivered over upcoming iterations.
- Servant leadership in retro
Show answerHide answer
Facilitate openly and safely so the team owns its improvements.
- Cumulative flow diagram
Show answerHide answer
An agile chart showing work in each state over time to reveal bottlenecks.
- Lead time vs. cycle time
Show answerHide answer
Lead time spans request to delivery; cycle time spans work start to finish.
- Daily standup three questions
Show answerHide answer
What did I do, what will I do, and what's blocking me?
- Product vision
Show answerHide answer
A clear, shared statement of the product's purpose guiding backlog priorities.
- Agile coaching
Show answerHide answer
Helping teams and organizations adopt agile mindsets and practices effectively.
Foundations & Mindset (24)
- PMP
Show answerHide answer
The Project Management Professional certification from PMI, validating the ability to lead and direct projects.
- PMI
Show answerHide answer
The Project Management Institute, the body that issues the PMP and publishes the PMBOK Guide.
- PMBOK Guide
Show answerHide answer
PMI's A Guide to the Project Management Body of Knowledge; the 7th edition is principle-based.
- Agile Practice Guide
Show answerHide answer
A PMI/Agile Alliance guide to agile and hybrid approaches, referenced by the PMP.
- PMP exam domains
Show answerHide answer
People (42%), Process (50%), and Business Environment (8%) on the current exam.
- PMP exam length
Show answerHide answer
180 questions in 230 minutes with one optional 10-minute break (current exam).
- PMP content mix
Show answerHide answer
About half the questions are agile or hybrid; the other half are predictive.
- PMP passing standard
Show answerHide answer
Pass/fail set by an expert panel; no fixed % cut score; per-domain ratings are reported.
- PMP score ratings
Show answerHide answer
Above Target, Target, Below Target, and Needs Improvement, reported per domain.
- PMP eligibility
Show answerHide answer
35 contact hours plus either a 4-year degree + 36 months or a HS/associate + 60 months leading projects.
- PMP validity & renewal
Show answerHide answer
Valid for 3 years; renew with 60 PDUs in PMI's Talent Triangle.
- New PMP exam (July 2026)
Show answerHide answer
Rebalances weights to People 33%, Process 41%, Business Environment 26%; same three domains.
- PMI mindset
Show answerHide answer
Be proactive, serve and empower the team, deliver value, and confront problems collaboratively.
- 12 PMBOK 7 principles
Show answerHide answer
Stewardship, team, stakeholders, value, systems thinking, leadership, tailoring, quality, complexity, risk, adaptability & resilience, change.
- 8 performance domains
Show answerHide answer
Stakeholders, team, development approach & life cycle, planning, project work, delivery, measurement, uncertainty.
- Tailoring
Show answerHide answer
Deliberately adapting the approach, processes, and artifacts to fit the specific project context.
- Project life cycle
Show answerHide answer
The phases a project moves through from start to close; can be predictive, iterative, incremental, or adaptive.
- Sponsor
Show answerHide answer
The person or group that funds and champions the project and is accountable for enabling its success.
- Triple constraint
Show answerHide answer
The balance among scope, schedule, and cost (with quality at the center).
- Process groups (predictive)
Show answerHide answer
Initiating, planning, executing, monitoring & controlling, and closing.
- Knowledge areas (PMBOK 6)
Show answerHide answer
Integration, scope, schedule, cost, quality, resource, communications, risk, procurement, and stakeholders.
- Talent Triangle
Show answerHide answer
PMI's skill model: Ways of Working, Power Skills, and Business Acumen.
- PDU
Show answerHide answer
A Professional Development Unit; 60 are needed every three years to maintain the PMP.
- Agile vs. predictive scope
Show answerHide answer
Agile flexes scope and fixes time/cost; predictive fixes scope and flexes time/cost.
References
- 1.Project Management Institute. “PMP Examination Content Outline (ECO).” pmi.org. ↑
- 2.Project Management Institute. “A Guide to the Project Management Body of Knowledge (PMBOK Guide), 7th ed..” pmi.org. ↑
- 3.Project Management Institute. “Agile Practice Guide.” pmi.org. ↑

Career Employer
Career Employer is the ultimate resource to help you get started working the job of your dreams. We cover topics from general career information, career searching, exam preparation with free study materials, career interviewing, and becoming successful in your career of choice.
All PostsCareer Employer’s Editorial Process
Here at Career Employer, we focus a lot on providing factually accurate information that is always up to date. We strive to provide correct information using strict editorial processes, article editing, and fact-checking for all of the information found on our website. We only utilize trustworthy and relevant resources. To find out more, make sure to read our full editorial process page here.
